On 28th February 2019, we completed the erection of 1800tpd Greenfield project for Palpa Cement Industry. The erection work was started on 15th of July 2018, and was completed within a span of 8 months, which is a record in Nepal. The Kiln Lightup was done today (8/3/2019) in the presence of HAPBCO and Palpa Cements staffs. We appreciate Mr Reji Mathew (Project Manager-HAPBCO,) and the entire HAPBCO team at Palpa Cements, for their collective performance and planning, complying with all safety standards and procedures for the successful completion of the project. Also we thank the Palpa Cement managements, for their support and co-operation, which helped us to achieve our goal.